Rubb, Inc. New Welding Shop Construction – Week 5

June 21st, 2008 by Glen

This was another slow construction week as some crews resumed normal shop and site duties.  More roof purlins were added and the bracing cables were tightened.  Most importantly, a few rolls of the PVC fabric were hoisted up and placed on the roof of the building, as shown in the video.  When the remaining rolls are fabricated and placed, they will be pulled down over the framework to form a watertight covering.

It has also been a wet week, with a thunderstorm nearly every day, playing havoc with the camera’s electronics from time to time.  Today, you can see the morning fog burn off and the puddle on the shop floor evaporate in the sun through the day.
 
 
 