Rubb, Inc. New Welding Shop Construction – Week 8
July 14th, 2008 by GlenThe bulk of the PVC sheets were unrolled and pulled over the framework this week. As of Friday, only one sheet remained to be installed. This puts the building 90% under cover, and once the sheets have been laced and heat-sealed together they can work inside installing the concrete floor and mezzanine.
In Thursday’s time-lapse video, two sheets are unrolled on the north side of the building and one on the south side in the morning. I went up on the roof for the south sheet to videotape the operation. Later that afternoon another sheet was hoisted up and placed on the roof to be unrolled on Friday.